● ()is the application ion of planned, systematic quality activities to ensure that the pr



● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs

答案解析

00****47 A质量保证是