考试
2020-03-15 21:22:11

8867 ● The earned value techni

题目描述

● The earned value technique is a commonly used method of performance measurement. It inte



● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.

(74)A.the project is ahead of its planned schedule

B.less work was completed than was planned

C.the cost overrun for work completed

D.the cost under-run of performance to date

答案解析

00****30 B参考译文挣

加载中...
AI正在思考中,请稍候...