9704 The()process ascertains w

题目描述

The()process ascertains which risks have the potential of affecting the project and doc



The()process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control

答案解析

00****17 A风险识别(