8315 The inputs of developing

题目描述

The inputs of developing project management plan do not include(72). A.project charter B



The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes

答案解析

00****47 B制定项目管