  用下面所提供的信息写一份实地考察报告:  What is thesnbject to be reported?  inspection of communication site at Pensacola  Forwhom is the report intended?  Cole—Myers Electric Company  HOW will the report be used?  to determine efficiency of present operation  Site Visited:communication site at Pensacola  Purpose of Visit:to inspect power supply,equipment room,and control room  Background Information:inspection requested by the letter of October 31,1992;  report written on November 28,1992  Facts,Details,and Results of the Investigation:transformers operat ing at peak operating condition;automatic switchover equipment working properly;converter equipment output has less than 3% distortion;no major outage since 0ctober 2,1987;muhiplex equipment adequate;one branch operating on auxiliary power with no backup;tO be corrected by the end of November;control room well supervised and efficiently operated  Conclusions and Recommendations: communication site at Pensacola one of the best in the area;personnel satisfied.sum of average outages:30 min.per week.

答案解析

  From:Writer

  To:Mr Rothchild

  Cole Meyer Electric Company

  Date:November 28,1992

  Novemher 28,1992

  Subject:Inspection of Communication Site at Pendacola

  In accordance with your letter of October 31,1987,I have made a personal inspection of the communication site at Pensacola and submit the following report.

  Power Supply

  Transformers:Thc transformers are in peak operating conditions. According to the log,two transformers are operating at the same time One supplies the power and the other is a standby.

  Automatic Switchover:The automatic switchover equipment is working properly.Standard tests were performed and not once did the signal lose phase from one transformer to another

  Equipment Room

  Converters:The converter equipment has an output with less than 3%distortion.A routine check for distortion is made every hour and recorded according tO regulations Very little outage is recorded and no major outage has been recoMedd since the cable cut of October 2,1987

  Muhiplex:The multiplex equipment is adequate with one exception.The second branch is operating on auxiliary power with no backup.A power supply has been ordered and should arrive November 28

  Control Room

  The control room is supervimd and everyone is well trained in control facilities.The outage record and the logs are kept accurately and upto date

  Conelusion

  The site at pensacola is one of the best in the area.The personnel are satisfied and no complaints were filed.The average outages add up to about 30 minutes a week,which is the best record in the area.