3011 Schedule development can

题目描述

Schedule development can require the review and revision of duration estimates and resou



Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule

答案解析

00****98 D制定进度表